Project Ägypten: Schedule
Home | Technology | Who | Schedule | Development | Public Relations | Glossary
The project is in the cleanup and maintenance phase. Upcoming bugs will be investigated.
Completed
Milestone 6, (27-November-2002, planned was end of August): Project accepted.
Milestone 5 (1-August-2002): External test finished.
Milestones 4.1 and 4.2 (29-April-2002): Smartcard connection, PKCS-15, KMail address book is connected, Presentation at CeBIT (13-20-March-2002), Integration in mutt.
Milestone 3 (19-February-2002): LDAP connection for CRL retrieval finished, creation and management for keys are integrated in KMail user interface. OpenPGP in KMail works analogous to S/MIME.
Planning of milestones revised (14-January-2002).
Milestone 2 (21-December-2001, planned was 26-November): Encryption, decryption, signing and signature checking works for KMail
Milestone 1 (29-October-2001): Implementation design and interface definitions ready to start implementation work